Ask the Customer Before Asking the Bank

Financing StrategyBorrower Advisory

Before a business borrows to fund a cash gap, it is worth checking what the gap would be under billing terms nobody has revisited since the first contract.

A mechanical contractor runs $24 million of revenue on jobs averaging $600,000 over four months. Work is billed monthly in arrears for what has been completed, 10 percent is withheld as retainage, approval and payment terms run to net 45, and payment typically arrives about sixty days after the billing month closes. Retainage is released at closeout.

That is a completely ordinary structure for the trade. Here is what it costs.

What one job ties up

Costs run at $127,500 a month for four months. Billings go out monthly, less retainage, and arrive two months later. Retainage comes back months after that.

Peak cash out on a single job is $255,000, which is 43 percent of the contract value. Across ten concurrent jobs, the business is carrying $2.55 million of its own money, permanently, because as one job finishes another starts.

At an illustrative 9 percent cost of funds, carrying it costs about $229,500 a year.

Two changes, neither of them financing

A 20 percent mobilization deposit, credited against the first billings. Peak cash out per job falls from $255,000 to $180,000. Across ten jobs that is $750,000 released.

Retainage reduced from 10 to 5 percent at half completion, with release at substantial completion rather than final closeout. This is an ordinary contract provision, not a concession anyone invented for this example. It takes the peak to $165,000 a job.

Together: $1.65 million carried instead of $2.55 million, and a carrying cost of $148,500 instead of $229,500.

Working capital released by changing billing terms at a mechanical contractor A callout of $900,000 of working capital released by two contract clauses, a 20 percent mobilization deposit and retainage reduced to 5 percent at half completion. Peak cash out on one job falls from $255,000 to $165,000. Across ten concurrent jobs the business carries $1.65 million instead of $2.55 million. Carrying cost at an illustrative 9 percent falls from $229,500 a year to $148,500. WORKING CAPITAL Ask the Customer Before Asking the Bank. A $24M mechanical contractor, jobs of $600,000 over four months. Monthly billing in arrears, 10 percent retainage, paid about 60 days later. $900,000 of working capital released by two contract clauses A 20 percent mobilization deposit, and retainage cut to 5 percent at half completion. WHAT CHANGES TODAY AFTER Peak cash out, one job $255,000 $165,000 Across ten concurrent jobs $2.55M $1.65M Carrying cost at 9 percent $229,500 a year $148,500 a year Source: Illustrative construction, arithmetic shown in the article | Thalos Capital Research Thalos Capital ©

$900,000 of working capital, released by two clauses. No facility, no interest, no covenant, no borrowing base.

Where customers actually push back

This is not free, and pretending otherwise is how these conversations fail.

Deposits raise a security question. A customer advancing 20 percent wants comfort that the money is used on their job. The usual answers are a payment bond, a schedule of values tied to mobilization costs the contractor can evidence, or a deposit sized to specific purchases such as long-lead equipment rather than to a round percentage.

Public work often prohibits advance payments outright. Many public owners cannot pay before work is performed, whatever the contract says. For that segment, the lever is billing frequency and retainage rather than deposits.

Retainage is a negotiation with a history. Reduction at half completion is common and frequently granted on request, particularly to a contractor with a clean closeout record. Reduction to zero is not, and asking for it tends to end the conversation.

Something gets traded. The usual currencies are a firmer schedule commitment, a modest price concession, or more frequent documentation. A contractor who offers one of those in exchange gets a different answer than one who simply asks.

Six stages, six levers
Where the cash cycle is set, and what to ask for at each
Every stage between signing and final payment is contractual. Most contractors negotiate one of them, and it is the hardest one to move.
The six stages of a contractor cash cycle and the lever at each Contract signed: a 20 percent mobilization deposit, sized to evidenced mobilization costs or long-lead equipment. Work in progress: billing frequency, where semi-monthly instead of monthly moves cash two weeks earlier. Each billing: retainage, where 10 percent falling to 5 percent at half completion is an ordinary clause. Billing approved: the approval window, with a named approver and an agreed submission format. Payment terms: net 45 and often later, the only stage most contractors negotiate and the hardest to move. Closeout: retainage released at substantial completion rather than final closeout, worth months of cash. STAGE THE LEVER WHAT TO ASK FOR Contract signed Mobilization deposit, 20% Sized to evidenced costs or long-lead equipment Work in progress Billing frequency Semi-monthly moves cash two weeks earlier, every job Each billing Retainage 10% to 5% at half completion, an ordinary clause Billing approved Approval window A named approver and an agreed submission format Payment terms Net 45, often paid later The one stage most negotiate, and the hardest to move Closeout Retainage release At substantial completion, not final closeout
Each lever is traded for something: a firmer schedule commitment, a payment bond on the deposit, more frequent documentation, or a modest price concession. A contractor who offers one of those gets a different answer than one who simply asks. Public owners are often barred from advance payments entirely, which leaves billing frequency and retainage as the available moves.
Source: Illustrative construction, arithmetic shown in the article | Thalos Capital Research Thalos Capital ©

What this does not fix

It would be convenient if the whole gap were negotiable. It is not.

Even under the better structure, the business still carries $1.65 million of its own cash, every month, and it still grows with revenue. That is the structural part, and it is what a facility should be sized against.

The order is what matters. A business that negotiates its terms first and then arranges a facility borrows $1.65 million. One that arranges the facility first borrows $2.55 million and never revisits the billing, because the pressure that would have forced the conversation has been removed.

How Thalos Capital Approaches This

Thalos Capital works borrower-side on working capital from $50 thousand to $100 million and above, across the United States. The starting point is the cash cycle rather than a facility size: when money goes out, when it comes back, and which parts of that timing are contractual rather than structural.

For a contractor that usually produces two outputs. A list of terms worth renegotiating on the next contract, which costs nothing to act on, and a facility sized against what is left, arranged against a receivables profile that is now shorter and cleaner.

The contractor in the example was not short of financing options. He had never asked his customers for terms he was entitled to request.

Most financing situations have more options than the borrower initially sees. A conversation is enough to map them. Submit your financing request at https://thaloscapital.com/contact.

Ready to map your options?
Most financing situations have more options than the borrower initially sees.
A conversation is enough to map them.